Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j30_a20_nr2 > Solution: 3049
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-18 198.45 278 146.75 44.305 PSGSMINSLK C 0 0
n/a
 
  Comment by author: PR - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 42 46 0 4 9.52 %
 Project 2 61 170 0 109 178.69 %
 Project 3 40 266 0 226 565.00 %
 Project 4 45 141 0 96 213.33 %
 Project 5 72 218 0 146 202.78 %
 Project 6 63 207 0 144 228.57 %
 Project 7 53 231 0 178 335.85 %
 Project 8 46 193 0 147 319.57 %
 Project 9 63 201 0 138 219.05 %
 Project 10 48 230 0 182 379.17 %
 Project 11 58 234 0 176 303.45 %
 Project 12 69 233 0 164 237.68 %
 Project 13 51 201 2 150 294.12 %
 Project 14 56 201 0 145 258.93 %
 Project 15 44 223 0 179 406.82 %
 Project 16 43 160 0 117 272.09 %
 Project 17 43 213 0 170 395.35 %
 Project 18 44 215 0 171 388.64 %
 Project 19 48 202 3 154 320.83 %
 Project 20 45 184 0 139 308.89 %