 Ranking & Analysis > Problem: mp_j30_a10_nr1 > Solution: 3030
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-18 169.7 189 135.7 17.0883 PSGSMINSLK C 0 0
n/a
 
  Comment by author: PR - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 34 149 0 115 338.24 %
 Project 2 34 178 8 144 423.53 %
 Project 3 34 180 0 146 429.41 %
 Project 4 34 183 0 149 438.24 %
 Project 5 34 188 7 154 452.94 %
 Project 6 34 141 0 107 314.71 %
 Project 7 34 162 3 128 376.47 %
 Project 8 34 154 0 120 352.94 %
 Project 9 34 189 0 155 455.88 %
 Project 10 34 173 0 139 408.82 %