MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
ResourceAgent - 2014-06-06 | 237.7 | 348 | 147.9 | 81.1164 | RLS | C | 100000 | 300 | 23 |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 86 | 296 | 0 | 210 | 244.19 % |
|
||
Project 2 | 82 | 101 | 0 | 19 | 23.17 % |
|
||
Project 3 | 78 | 138 | 0 | 60 | 76.92 % |
|
||
Project 4 | 83 | 162 | 0 | 79 | 95.18 % |
|
||
Project 5 | 83 | 188 | 0 | 105 | 126.51 % |
|
||
Project 6 | 105 | 242 | 0 | 137 | 130.48 % |
|
||
Project 7 | 97 | 281 | 45 | 184 | 189.69 % |
|
||
Project 8 | 109 | 290 | 0 | 181 | 166.06 % |
|
||
Project 9 | 90 | 331 | 38 | 241 | 267.78 % |
|
||
Project 10 | 85 | 348 | 0 | 263 | 309.41 % |
|