MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Xiaoyu Mao - 2010-07-14 | 390 | 729 | 316 | 199.344 | Fwd/Bwd | C | 13 | 5 | n/a |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 74 | 96 | 0 | 22 | 29.73 % |
|
||
Project 2 | 74 | 157 | 0 | 83 | 112.16 % |
|
||
Project 3 | 74 | 220 | 0 | 146 | 197.30 % |
|
||
Project 4 | 74 | 287 | 26 | 213 | 287.84 % |
|
||
Project 5 | 74 | 362 | 162 | 288 | 389.19 % |
|
||
Project 6 | 74 | 428 | 161 | 354 | 478.38 % |
|
||
Project 7 | 74 | 496 | 222 | 422 | 570.27 % |
|
||
Project 8 | 74 | 558 | 259 | 484 | 654.05 % |
|
||
Project 9 | 74 | 612 | 257 | 538 | 727.03 % |
|
||
Project 10 | 74 | 684 | 252 | 610 | 824.32 % |
|