SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 137.4 | 162 | 48.1 | 13.2451 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 94 | 125 | 0 | 31 | 32.98 % |
|
||
Project 2 | 85 | 133 | 0 | 48 | 56.47 % |
|
||
Project 3 | 70 | 96 | 0 | 26 | 37.14 % |
|
||
Project 4 | 83 | 137 | 0 | 54 | 65.06 % |
|
||
Project 5 | 72 | 139 | 0 | 67 | 93.06 % |
|
||
Project 6 | 105 | 153 | 0 | 48 | 45.71 % |
|
||
Project 7 | 91 | 155 | 0 | 64 | 70.33 % |
|
||
Project 8 | 107 | 162 | 0 | 55 | 51.40 % |
|
||
Project 9 | 87 | 125 | 0 | 38 | 43.68 % |
|
||
Project 10 | 99 | 149 | 0 | 50 | 50.51 % |
|