MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 161.5 | 185 | 61.6 | 8.6564 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 77 | 140 | 0 | 63 | 81.82 % |
|
||
Project 2 | 88 | 140 | 0 | 52 | 59.09 % |
|
||
Project 3 | 91 | 155 | 0 | 64 | 70.33 % |
|
||
Project 4 | 108 | 168 | 0 | 60 | 55.56 % |
|
||
Project 5 | 115 | 185 | 0 | 70 | 60.87 % |
|
||
Project 6 | 100 | 172 | 0 | 72 | 72.00 % |
|
||
Project 7 | 87 | 162 | 0 | 75 | 86.21 % |
|
||
Project 8 | 102 | 157 | 0 | 55 | 53.92 % |
|
||
Project 9 | 103 | 157 | 0 | 54 | 52.43 % |
|
||
Project 10 | 128 | 179 | 0 | 51 | 39.84 % |
|