.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 133 | 151 | 42.1 | 8.53034 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 99 | 131 | 0 | 32 | 32.32 % |
|
||
Project 2 | 79 | 110 | 0 | 31 | 39.24 % |
|
||
Project 3 | 88 | 118 | 0 | 30 | 34.09 % |
|
||
Project 4 | 96 | 151 | 0 | 55 | 57.29 % |
|
||
Project 5 | 89 | 136 | 0 | 47 | 52.81 % |
|
||
Project 6 | 88 | 131 | 0 | 43 | 48.86 % |
|
||
Project 7 | 96 | 141 | 0 | 45 | 46.88 % |
|
||
Project 8 | 91 | 142 | 0 | 51 | 56.04 % |
|
||
Project 9 | 95 | 138 | 0 | 43 | 45.26 % |
|
||
Project 10 | 88 | 132 | 0 | 44 | 50.00 % |
|