SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 128.5 | 151 | 37.6 | 17.1088 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 99 | 118 | 0 | 19 | 19.19 % |
|
||
Project 2 | 79 | 100 | 0 | 21 | 26.58 % |
|
||
Project 3 | 88 | 97 | 0 | 9 | 10.23 % |
|
||
Project 4 | 96 | 130 | 0 | 34 | 35.42 % |
|
||
Project 5 | 89 | 128 | 0 | 39 | 43.82 % |
|
||
Project 6 | 88 | 127 | 0 | 39 | 44.32 % |
|
||
Project 7 | 96 | 148 | 0 | 52 | 54.17 % |
|
||
Project 8 | 91 | 144 | 0 | 53 | 58.24 % |
|
||
Project 9 | 95 | 142 | 0 | 47 | 49.47 % |
|
||
Project 10 | 88 | 151 | 0 | 63 | 71.59 % |
|