.: Analysis |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 272.6 | 389 | 182.5 | 109.517 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 73 | 116 | 0 | 43 | 58.90 % |
|
||
Project 2 | 74 | 389 | 0 | 315 | 425.68 % |
|
||
Project 3 | 68 | 386 | 0 | 318 | 467.65 % |
|
||
Project 4 | 89 | 389 | 0 | 300 | 337.08 % |
|
||
Project 5 | 100 | 204 | 0 | 104 | 104.00 % |
|
||
Project 6 | 104 | 161 | 0 | 57 | 54.81 % |
|
||
Project 7 | 117 | 186 | 0 | 69 | 58.97 % |
|
||
Project 8 | 96 | 334 | 0 | 238 | 247.92 % |
|
||
Project 9 | 97 | 268 | 0 | 171 | 176.29 % |
|
||
Project 10 | 83 | 293 | 0 | 210 | 253.01 % |
|