 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp6 > Solution: 3868
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 272.6 389 182.5 109.517 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 73 116 0 43 58.90 %
 Project 2 74 389 0 315 425.68 %
 Project 3 68 386 0 318 467.65 %
 Project 4 89 389 0 300 337.08 %
 Project 5 100 204 0 104 104.00 %
 Project 6 104 161 0 57 54.81 %
 Project 7 117 186 0 69 58.97 %
 Project 8 96 334 0 238 247.92 %
 Project 9 97 268 0 171 176.29 %
 Project 10 83 293 0 210 253.01 %