.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-23 | 210.8 | 274 | 121 | 28.4878 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 86 | 199 | 0 | 113 | 131.40 % |
|
||
Project 2 | 82 | 253 | 0 | 171 | 208.54 % |
|
||
Project 3 | 78 | 163 | 0 | 85 | 108.97 % |
|
||
Project 4 | 83 | 186 | 0 | 103 | 124.10 % |
|
||
Project 5 | 83 | 233 | 0 | 150 | 180.72 % |
|
||
Project 6 | 105 | 211 | 4 | 106 | 100.95 % |
|
||
Project 7 | 97 | 238 | 3 | 141 | 145.36 % |
|
||
Project 8 | 109 | 215 | 0 | 106 | 97.25 % |
|
||
Project 9 | 90 | 234 | 0 | 144 | 160.00 % |
|
||
Project 10 | 85 | 176 | 0 | 91 | 107.06 % |
|