 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp8 > Solution: 3726
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 241.2 345 158.8 81.8273 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 86 196 0 110 127.91 %
 Project 2 82 345 4 263 320.73 %
 Project 3 78 148 0 70 89.74 %
 Project 4 83 208 0 125 150.60 %
 Project 5 83 309 0 226 272.29 %