 Ranking & Analysis > Problem: mp_j120_a20_nr3 > Solution: 3505
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 146.45 244 53.25 32.8455 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 120 0 21 21.21 %
 Project 2 79 111 0 32 40.51 %
 Project 3 88 110 0 22 25.00 %
 Project 4 96 162 0 66 68.75 %
 Project 5 89 135 0 46 51.69 %
 Project 6 88 119 0 31 35.23 %
 Project 7 96 210 0 114 118.75 %
 Project 8 91 229 0 138 151.65 %
 Project 9 95 188 0 93 97.89 %
 Project 10 88 138 0 50 56.82 %
 Project 11 105 141 0 36 34.29 %
 Project 12 89 139 0 50 56.18 %
 Project 13 69 114 0 45 65.22 %
 Project 14 111 156 0 45 40.54 %
 Project 15 97 123 0 26 26.80 %
 Project 16 72 117 0 45 62.50 %
 Project 17 111 151 1 40 36.04 %
 Project 18 114 131 0 17 14.91 %
 Project 19 97 196 0 99 102.06 %
 Project 20 90 139 0 49 54.44 %