 Ranking & Analysis > Problem: mp_j120_a20_nr3 > Solution: 3504
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 145.65 238 52.45 32.0747 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 129 0 30 30.30 %
 Project 2 79 104 0 25 31.65 %
 Project 3 88 102 0 14 15.91 %
 Project 4 96 152 0 56 58.33 %
 Project 5 89 147 0 58 65.17 %
 Project 6 88 116 0 28 31.82 %
 Project 7 96 221 0 125 130.21 %
 Project 8 91 223 0 132 145.06 %
 Project 9 95 189 0 94 98.95 %
 Project 10 88 140 0 52 59.09 %
 Project 11 105 147 0 42 40.00 %
 Project 12 89 137 0 48 53.93 %
 Project 13 69 108 0 39 56.52 %
 Project 14 111 155 0 44 39.64 %
 Project 15 97 124 0 27 27.84 %
 Project 16 72 113 0 41 56.94 %
 Project 17 111 165 0 54 48.65 %
 Project 18 114 129 0 15 13.16 %
 Project 19 97 166 0 69 71.13 %
 Project 20 90 146 0 56 62.22 %