SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Ameisenbaer - 2011-02-27 | 120.5 | 181 | 55.5 | 39.2266 | AB_CMACS | C | 1 | 1 | 19 |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 65 | 79 | 0 | 14 | 21.54 % |
|
||
Project 2 | 65 | 78 | 0 | 13 | 20.00 % |
|
||
Project 3 | 65 | 79 | 0 | 14 | 21.54 % |
|
||
Project 4 | 65 | 87 | 0 | 22 | 33.85 % |
|
||
Project 5 | 65 | 114 | 0 | 49 | 75.38 % |
|
||
Project 6 | 65 | 122 | 0 | 57 | 87.69 % |
|
||
Project 7 | 65 | 145 | 0 | 80 | 123.08 % |
|
||
Project 8 | 65 | 155 | 0 | 90 | 138.46 % |
|
||
Project 9 | 65 | 165 | 0 | 100 | 153.85 % |
|
||
Project 10 | 65 | 181 | 0 | 116 | 178.46 % |
|