MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Dietz/Homberger - 2008-06-25 | 188.8 | 264 | 93.5 | 29.975 | CMAS/ES | D | 100000 | 1010.19 | 6 | |
Comment by author: Mue:50 Lambda:100 Rounds:1000 |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 99 | 162 | 0 | 63 | 63.64 % |
|
||
Project 2 | 89 | 222 | 0 | 133 | 149.44 % |
|
||
Project 3 | 110 | 197 | 0 | 87 | 79.09 % |
|
||
Project 4 | 91 | 189 | 0 | 98 | 107.69 % |
|
||
Project 5 | 98 | 249 | 0 | 151 | 154.08 % |
|
||
Project 6 | 114 | 220 | 0 | 106 | 92.98 % |
|
||
Project 7 | 103 | 164 | 0 | 61 | 59.22 % |
|
||
Project 8 | 79 | 173 | 0 | 94 | 118.99 % |
|
||
Project 9 | 77 | 149 | 0 | 72 | 93.51 % |
|
||
Project 10 | 93 | 163 | 0 | 70 | 75.27 % |
|