.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Dietz/Homberger - 2008-05-10 | 111.9 | 146 | 61.2 | 16.9365 | RES | C | 0 | 0 | n/a |
|
Comment by author: Automatic Webservice Upload - Central method (evolutionary metaheuristic) published in: Homberger, J. 2007. A Multi-agent System for the Decentralized Resource-constrained Multi-project Scheduling Problem. International Transactions in Operational Research, 14(6): 565-589. |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 48 | 144 | 0 | 96 | 200.00 % |
|
||
Project 2 | 42 | 116 | 0 | 74 | 176.19 % |
|
||
Project 3 | 35 | 105 | 0 | 70 | 200.00 % |
|
||
Project 4 | 63 | 110 | 0 | 47 | 74.60 % |
|
||
Project 5 | 49 | 114 | 0 | 65 | 132.65 % |
|
||
Project 6 | 44 | 109 | 0 | 65 | 147.73 % |
|
||
Project 7 | 70 | 106 | 0 | 36 | 51.43 % |
|
||
Project 8 | 49 | 103 | 0 | 54 | 110.20 % |
|
||
Project 9 | 56 | 114 | 0 | 58 | 103.57 % |
|
||
Project 10 | 51 | 98 | 0 | 47 | 92.16 % |
|